CAY HILL:--- St. Maarten Medical Center (SMMC) is pleased with the latest pouring of the next section of St. Maarten General Hospital (SMGH)’s basement floor, which was successfully completed on Wednesday, February 23, 2022.
FINSO, the general contractor of SMGH, its main concrete supplier St. Maarten Concrete and other stakeholders successfully completed the pour of approx. 700 cubic meters of high-quality concrete which took 86 cement trucks in total: a first for St. Maarten. This was the 4th pour in a total of 7 scheduled pours before the SMGH basement floor is completed, which started on Tuesday at 5 pm ...
...
To read more: https://www.smn-news.com/index.php/st-maarten-st-martin-news/39764-smmc-pleased-with-successful-largest-pour.html