PHILIPSBURG:--- On Friday, July 29th, the Minister of Public Health, Social Development, and Labor, visited the Sint Maarten General Hospital (SMGH) project site to witness the largest pour-in Sint Maarten's history, which was 700 cubic meters. The historic pour of section 6 started at 3 pm and lasted 22 hours. The last update from the Minister was given during the pour of sections 4 & 5, which together totaled 400 cubic meters.
At that time the Finso company and the SMGH contract manager projected the pouring of section 6 to commence somewhere around July 22nd, 2022. “The pour was delayed ...
...