GEBE apologized to residents for Island wide blackout Monday night.

January 17, 2017

GEBE apologized to residents for Island wide blackout Monday night.
Loading...

PHILIPSBURG:--- In a press release from NV GEBE the company apologized to each and every client that was inconvenienced and affected during the power interruption on the night of January 16, 2016, at approximately 21:15 hours during the island-wide blackout.
The island-wide blackout started when one of the company’s 8 MW engines encountered a shutdown “trip” command from a sensor. This “trip” resulted in an unstable power grid and caused the other engines to react in order to stabilize the grid. The process took place in a very short timeframe. As a result, it triggered the high voltage system to open which protects the equipment’s systems.
The power plant personnel resorted to the plant's protection in order to ensure a smooth startup which has to be done with safety for all.
The restarting process took some time as it first needed to be assessed as to what caused the total black out. Some equipment’s were isolated to be sure that everything was in order when restarting the engines. Once it was clear that it was safe to commence with the starting up process, the restoration plan was put into motion.
The first cable to be restored was the Cay Hill area as GEBE always gives priority to the St. Maarten Medical Center. In the process of restoring the power GEBE encountered some challenges and the plant went back down.
Upon restarting the plant again the process to restore all cables continued. At about 3:00 am all areas were restored with power. The power plant crew continued to rectify the entire system after the last cable was operational again, this entail full restoration of the cooling water system, the steam system, the fuel system, etc. GEBE would like to thank it’s staff that came out to assist with the restoration of power during the night.
GEBE is looking into this matter to avoid this from repeating and limiting the outages in the future. It is our intention to minimize the effects such loss of power has on the island. Once more we do apologize for the discomfort during the outage last night.
Additionally on Tuesday afternoon there was a software glitch that caused one of the engines to shut down and a number of areas were without power. This matter was quickly resolved and power was restored to the affected areas.

Loading...

GEBE apologized to residents for Island wide blackout Monday night.

Source: http://www.sxm-talks.com/st-martin-news-network/gebe-apologized-to-residents-for-island-wide-blackout-monday-night/

Loading...

Headlines

GEBE given until July 27 to justify  fuel-clause increase for BTP review | The Daily Herald

July 22, 2026

GEBE given until July 27 to justify fuel-clause increase for BTP review | The Daily Herald

Head of BTP. Judianne Labega-Hoeve during meeting with Minister of TEATT, Grisha Heyliger-Marten, TEATT Chief of Staff, Otmar Jonis and Legal Council to the Minister of TEATT, Joeri Essed. POND ISLAND--The Bureau Telecommunication and Post (BTP) has given utilities company NV...

July 21, 2026

Scooter rider was arrested Monday morning with firearm | Soualiganewsday

SINT MAARTEN (GREAT BAY) - On July 20th, at approximately 9:50 p.m., officers of the Korps Politie Sint Maarten (KPSM) Patrol Unit were conducting a routine patrol when they observed an individual riding a scooter. Officers attempted to stop the rider for a control;...

July 20, 2026

The Ministry of VSA and the Inspectorate of VSA is issuing the following alert! | Government of Sint Maarten

​Due to yet unknown reasons a large quantity of fish has been found dead in the communicating channel between Fresh Pond and Great Salt Pond, near the Illidge Road turnabout. The heat and direct sunlight are speeding up the rotting process and is producing a very unpleasant st...

Loading...
Loading...
Loading...