PJIAE Operations to move back to Terminal Building.

September 19, 2018

PJIAE Operations to move back to Terminal Building.
Loading...

~Completion of Terminal Building Scheduled for 2020~

AIRPORT:--- Management of the Princess Juliana International Airport (PJIAE) expects to move the airport operations back into the Terminal Building in November 2018. The new location will be temporary until the entire Terminal Building is restored.
Chief Operations Officer Michel Hyman told SMN News that the waterproofing of the Terminal Building roof has been completed and now they are busy with the second phase while they hired the services of BMS Cat that is also busy with the mold remediation. BES Cat is a company that hails from Texas and they are specialized in mold remediation.
At the moment some 60 persons are working for BMS Cat as they clean the building with special types of chemicals.
Hyman said that BMS Cat began the mold remediation in August and they are expected to complete the assignment by the end of September. The COO said that the remediation is taking place in an area they have described as package one which is where they intend to move in November temporarily to conduct the day to day operations of the airport. He said as of November both arrivals and departures will take place in the airport terminal building even though construction and other repairs will continue in other parts of the terminal building.
The intention is to have six gates, departure, arrivals as well as the concessionaires inside the terminal building. Even though the area would be much smaller the airport management team is doing all they can to ensure that the airlines, customs, immigration and the administration staff have working space.
Hyman further explained that while construction work will continue within the building the overall target date for the completion will be by the end of the first quarter of 2020. Hyman said that the Airport Terminal Building is a four-layer building and they have to ensure that everywhere is thoroughly cleaned to remove all the mold before they could occupy the entire building.
Regarding the financing for the renovation and rebuilding of the terminal building, Hyman said that the managing board is still busy with the insurance company to ensure that all the finances are in place. He made clear that the insurance claims have not been completed as yet but they are also working on other options to ensure that the terminal building is fully restored.
SMN News conducted a tour of the Terminal Building to get a view on the restoration of the terminal building. During that tour, it is clear that PJIAE terminal building got extensive wind and water damage which also damaged all their equipment’s belonging to the airport and the airlines.

Loading...

Click here to view more photos of inside PJIAE Terminal Building.

http://www.smn-news.com/st-maarten-st-martin-news/30124-pjiae-operations-to-move-back-to-terminal-building.html

Source: https://www.sxm-talks.com/st-martin-news-network/pjiae-operations-to-move-back-to-terminal-building/

Loading...

Headlines

Motorcyclist dies after  crash on Link 1 road | The Daily Herald

September 04, 2026

Motorcyclist dies after crash on Link 1 road | The Daily Herald

Rider of a Kawasaki Z650, plate MF 1397, died on September 4, following a motorcycle accident on Link 1. BELAIR--A motorcyclist has died following a serious single-vehicle accident on Octavius L. Richardson Road also known as Link 1 on Friday morning. The accident occurred at...

September 01, 2026

Armed robbery at Maho  casino under investigation | The Daily Herald

 MAHO--Police are investigating an armed robbery at Casino Royale in Maho around midday on Tuesday.   The Police Force of St. Maarten (KPSM) Central Dispatch received several calls reporting that an armed robbery was taking place at about 12:00pm on September 1. Seve...

September 01, 2026

St. Maarten still does not know officially what it costs to live here | The Peoples Tribune

GREAT BAY--St. Maarten does not currently have an officially established social minimum defining how much money an individual or household needs to cover essential living expenses and participate normally in society. That fact means that while government provides millions of g...

Loading...
Loading...
Loading...