SIMPSON BAY:—The reconstruction works to finalize the roof betterment at the Princess Juliana International Airport, SXM is scheduled to be completed in May 2019. According to the official progress report from Project Manager Rob Noorman, Phase II of the roof repair works of the installation of the Riverclack roof sheeting is almost completed. The finishing works, and installation of the five roof expansion joints are slated to be executed early May 2019. Phase III of the roof repairs consists of the installation of the bullnoses and soffits along the perimeter of the roof and are scheduled to be finalized